Local Plan timetable

The government has published guidance that requires all local authorities to adjust the way they prepare Local Plans. This means we’ve had to review and replace our original plan making timetable (known as the Local Development Scheme) to ensure we meet the new legal requirements.

Work is already underway and progress has already been made. As a result of the new national guidance, our overall timetable will aim for adoption of the plan by April 2029.

The new timetable formally replaces our Local Development Scheme. Below is the current timetable for preparing the new St Albans Local Plan 2029, which will cover the administrative area of St Albans City & District. This timetable may be updated as the Plan progresses.

This timetable takes effect from 25 June 2026.

Plan eventDate
Publish Notice of Intention to Commence Plan-making25 June 2026
Scoping Consultation start - end3 August – 14 September 2026
Gateway 1 Self Assessment26 October 2026
Plan Content and Evidence Consultation start - end12 April – 25 May 2027
Gateway 2 Advice sought27 September 2027
Proposed Plan Consultation start - end17 April – 13 June 2028
Gateway 3 Advice sought28 August 2028
Submission of the proposed Local Plan to the Secretary of State for independent examination30 October 2028
Adopted27 April 2029

Local Plan Timetable (Download in PDF format)

 

Local Plan Timetable CSV Download

This data is provided under the Open Government Licence.